Facility

Watch with us as our new facility begins to take shape and come to life.  Check back periodically to see the latest progress.

Building completed and fully operational! - March 2020.
Siding and roof installation has started in the expanded facility. - November 2019.
New lighting installed in the fabricating facility. - November 2019.
Initial steel structure going in place and the expanded plant starts to take form. - October 2019.
Initial pad of concrete poured in new expansion area which will eventually become part of the insulating manufacturing and warehouse areas of the plant. - September 2019.
Early excavation of surrounding ground in preparation for 112,000 square foot expansion. - Early August 2019.
50,000 square foot facility built by Marshall County Economic Development Corporation (MCEDC) as purchased by Sequel in July 2019.